List of Commission's Orders / Judgments passed in various cases.





Sr.No. Petition No. Filed By Subject Matter Date of Final Decision
1 Review Petition No. 01 of 2018 in Petition No. 03 of 2017 Punjab State Power Corporation Limited Review Petition under Section 64 of the Punjab State Electricity Regulatory Commission (Conduct of Business) Regulations, 2005, praying for review of the Order dated 28.02.2018 passed by the Commission in Petition No. 03 of 2017 titled as Punjab State Power Corporation Limited V/s The Northern Railways and another. 21.05.2018
 
2 Review Petition No.03 of 2018 in Petition No. 65 of 2017 Punjab State Transmission Corporation Limited Review Petition under Section 94 (1) (f) of the Electricity Act, 2003 read with Order 47 Rule of the Code of Civil Procedure, 1908 and Regulation 64 of the Punjab State Electricity Regulatory Commission (Conduct of Business) Regulations, 2005 for seeking review of the Tariff Order dated 19.04.2018 passed by the Commission in Petition 65 of 2017 for FY 2018-19. 11.10.2018
 
3 Review Petition No.04 of 2018 in Petition No.: 64 of 2017 Punjab State Transmission Corporation Ltd. Review Petition under Regulation 64 of PSERC (Conduct of Business) Regulations, 2005 against PSERC Order dated 07.05.2018 in Petition No. 64 of 2017 for refund of security (works) in excess of actual expenditure 26.09.2018
 
4 06/2018 Punjab State Power Corporation Limited Petition under section 23 of the Electricity Act, 2003 seeking regulatory guidance for measures to be taken in case of exigencies leading to power cuts for the Tariff Year 2018-19. 03.04.2018
04.05.2018
 
5 07/2018 Satia Industries Limited Petition under Regulation 69, 71 & 72 of the Punjab State Electricity Regulatory Commission (Conduct of Business) Regulations, 2005 and any other Regulation of the Punjab State Electricity Regulatory Commission, read with provisions of the Electricity Act, 2003 seeking quashing/setting aside the communication dated 19.12.2017 issued by CE/Commercial-PSPCL, whereby, the request of the petitioner made by way of communication dated 21.11.2017 to transfer power from its Biomass Fired Captive Power Plants set up in the factory premises to the Pump Sets installed on the wholly owned Agricultural Land of the Petitioner–Company has been wrongly declined and the Petitioner has been conveyed that such case will be treated as Unauthorized Use of Electricity while wrongly applying and interpreting Section 36(e) of the Supply Code 2014. 04.06.2018
 
6 09/2018 Nahar Industrial Enterprises Limited and Others Petition under Section 9, 61 (h) and (i) read with Section 86(1)(e), 86(4) of the Electricity Act, 2003, read with Clause 9 & 10 of the “Punjab State Electricity Regulatory Commission (Harnessing of Captive Power Generation) Regulations, 2009” for their amendment/clarification so as to make adequate provisions for levying reasonable fixed charges in respect of load/demand fed from T.G./C.P.P./Co-Generation installed by various Industries as per Govt. Policies issued from time to time keeping in view shift in Punjab from Single Part Tariff to Two Part Tariff in the Tariff Order dated 23.10.2017.
AND
During the pendency of present Petition, applicability of “Two Part Tariff” be deferred till finalization of the amended Regulations in respect of Class of Industrial Consumers having installed T.G./C.P.P./Co-Generation with due permission from Distribution Licensee/Chief Electrical Inspector. In the meanwhile, till the present petition is decided, only energy charges as fixed by the Commission in Tariff Orders issued hereinafter, including deferred applicability of Tariff Order dated 23.10.2017 may be ordered.
06.07.2018
 
7 10/2018 Punjab State Power Corporation Limited Petition for determination of Additional Surcharge under Section 42 (4) of the Electricity Act, 2003, read with Regulation 27 of the Punjab State Electricity Regulatory Commission (Terms and Conditions for Intra-state Open Access) Regulations, 2011 to be made applicable on the open access consumers availing power from the sources other than Punjab State Power Corporation Limited for the period 01.04.2018 to 30.09.2018. 27.03.2018

04.05.2018
 
8 11/2018 Punjab State Power Corporation Limited Petition for approval of Fuel Cost Adjustment (FCA) Surcharge for 3rd quarter (October, 2017 to December, 2017) of FY 2017-18. 05.04.2018
 
9 12/2018 Punjab State Power Corporation Limited Petition for approval under regulation 86(1)(b) of the Electricity Act, 2003 for the Power Procurement plan on Short Term basis for the year 2018-19 read with the Public Notice issued by the Punjab State Electricity Regulatory Commission dated 23.10.2012. 24.05.2018
 
10 15/2018 Mandi Gobindgarh Induction Furnace Association Petition seeking issuance of the Tariff Order for the year 2018-19, in the matter of Petition No. 66 of 2017 filed by PSPCL, for Annual Performance Review and Retail Tariff for the year 2018-19 and Revised Estimates for the Year 2019-20, within 120 days of submission of the said petition as per Section 64 (3) of the Electricity Act, 2003 and Regulation 62 and 63 of the “Punjab State Electricity Regulatory Commission (Terms and Conditions for Determination of Generation, Transmission, Wheeling and Retail Supply Tariff) Regulations, 2014” (MYT Regulations).
AND
For implementing the Retail Tariff for the year 2018-19 prospectively, as per Regulation 52 of the Punjab State Electricity Regulatory Commission (Conduct of Business) Regulations, 2005 (as amended up to date), i.e. effective from the date of issue of order plus 7 days for allowing the members of the Petitioner-Association to understand the consequences of changes in retail tariff and effective changes / transfer the effect of change of retail tariff in the sale price of their products based on the revised cost of power.
AND
Pass any such further orders as this Hon’ble Commission may deem fit in the facts and circumstances of the case.
06.07.2018
 
11 18/2018 Punjab State Power Corporation Limited Petition under Regulation 8.1(b) of the Supply Code 2014 by Punjab State Power Corporation Limited for seeking approval of Hon’ble Commission for extension in time period of release of EHT connection.
And
New Connection of 4500 kW Load / 5000 kVA Contract demand applied by Divisional Railway Manager (Elect./TRD), New Delhi through Sr. Divisional Electrical Engineer (TRD), State Entry Road, BRM Office, Northern Railway, New Delhi under the category of Railway Traction in Sub Division Suburban Maur, PSPCL.
11.06.2018
 
12 19/2018 Punjab State Power Corporation Limited Petition under Regulation 6.3.2 of the Supply Code 2014 by Punjab State Power Corporation Limited for seeking approval of the Commission for extension in time period for Feasibility Clearance for release of EHT connection. 06.08.2018
 
13 20/2018 Canal Solar Energy Private Limited Petition seeking compliance of clause 10.1.5 of Power Purchase Agreement under applicable provisions of the Electricity Act, 2003 read with Regulation 69 (Saving of inherent power of the Commission), 71 (Power to remove difficulties) and 73 (Extension or abridgement of time allowed) of the Punjab State Electricity Regulatory Commission (Conduct of Business) Regulations, 2005. 31.10.2018
 
14 21/2018 Punjab State Power Corporation Limited (PSPCL) Petition for approval of Fuel Cost Adjustment (FCA) Surcharge for 4th quarter (January, 2018 to March, 2018) of FY 2017-18. 20.07.2018
 
15 22/2018 Punjab State Power Corporation Limited Clarification by PSPCL under provisions 4.1 and 4.5 of the Punjab State Electricity Regulatory Commission (Forum and Ombudsman) Regulations, 2016 against the order dated 28.08.2017 whereby the Ld. CGRF, Patiala has held that amount charged vide notice bearing no. 719 dated 25.05.2017 is not chargeable in case of CG 157/2017 of CGRF Patiala decided on 28/08/2017 M/s Kay Jay Forging, C-3, C-4, Focal Point, Ludhiana. 04.09.2018
 
16 23/2018 Suo-Motu Determination/ fixation of levellised generic Tariff for Renewable Energy Power Projects for FY 2018-19. 09.08.2018
 
17 26/2018 Bhawani Castings Pvt. Ltd. Petition under Section 142, 146, 149 read with other relevant provisions of the Electricity Act, 2003 and Regulation 68, 69 and 71 and provisions of Chapter XI of Punjab State Electricity Regulatory Commission (Conduct of Business) Regulations, 2005 as amended up to date and other relevant rules and regulations as approved by the Commission for directing the Respondent to refund the amount receivable by the Petitioner on account of threshold consumption for the year 2016-17, in line with the directions issued by this Commission vide communication dated 07.03.2018;
AND
For directing the Respondent to refund the ED, IDF, along with Penal Interest thereof, in line with the statement made by the Respondent before this Commission while adjudication of Petition No. 42 of 2017 inter-alia filed by the Petitioner.
28.09.2018
 
18 27/2018 Siel Chemical Complex Petition under Section 142 and Section 62(6) of the Electricity Act, 2003 for violation of Tariff Order for Financial Year 2018-19 by PSPCL. 17.10.2018
 
19 29/2018 Punjab State Power Corporation Limited Petition for the Determination of Additional Surcharge U/S 42 (4) of the Indian Electricity Act-2003 read with Regulation 27 of Punjab State Electricity Regulatory Commission (Terms and Conditions for Intra-State Open Access) Regulation -2011 to be made applicable on to the open access consumers availing power from the sources other than PSPCL for the period 01.10.2018 to 31.03.2019. 25.09.2018